Sign permits in Phoenix: what you need and how long it takes
Phoenix requires a sign permit for most signs before they're put up, moved or changed, with limited exceptions in Section 705 of the zoning ordinance. You'll need a site plan, sign drawings, electrical details if it's lit, and often sealed plans for larger signs.
Have us handle your permit Call (623) 297-3457
ROC license holder

Step 1: Define the sign type and location
Write down what you're installing: wall, monument or pylon sign, its size and height, whether it's lit and whether it reuses an existing structure. These details decide which rules apply. Phoenix Section 705 is the rule to read first in Phoenix.
Step 2: Check your landlord's sign criteria
Many shopping centers have their own sign rules on top of the city's. Get written approval from the property owner, since cities such as Tempe ask for that authorization when you apply.
Step 3: Prepare drawings, site plan and electrical details
Most cities want the same core package.
- Site plan showing the location of the sign.
- Elevations and details showing size, materials, colors and mounting.
- Electrical details for lit signs.
- Sealed plans when the sign's size or type calls for them.
Step 4: Confirm the electrical standards for lit signs
Lit signs are installed under Article 600 of the National Electrical Code and listed under UL 48. Building to both from the start makes the final inspection simpler.
Step 5: Submit the application and plan for review time
Review times and rules vary by city. We checked these on the cities' own pages on November 4, 2026, and they can change.
| City | Published review time | Worth knowing |
|---|---|---|
| Phoenix | Not published on the code page | Larger signs may need plans sealed by an Arizona engineer or architect |
| Scottsdale | 5 business days per review cycle | Temporary banners have a separate application |
| Tempe | 6 to 10 business days for first review | Sealed drawings for wall signs projecting 16 inches or more and freestanding signs 8 feet or taller |
| Mesa | 10 business days | Expedited review of 5 business days per cycle, at an added fee |
Step 6: Schedule the inspection and keep the permit tag visible
Book your city's inspection after installation. In Phoenix, permitted signs must show a readable permit tag, and electric signs also need an electrical compliance tag.
How Mas Color Signs handles the permit for you
Founder Jesús Ortega holds an Arizona ROC license and has worked with sign codes across the state. On your project, we check the rules for your address, prepare the package, submit it, answer city comments and coordinate the inspection. You can check any contractor's license with the Arizona Registrar of Contractors. This page is general information, not legal advice; your city has the final word.
Sign permit questions from business owners
Do I always need a permit for a sign in Phoenix?
Nearly always. Section 705 lists exceptions, such as signs that can't be seen from public streets or neighboring properties. If you're not sure, ask us or the city.
Who can apply for the permit?
In Phoenix, the owner, tenant or lessee can apply, as can an authorized agent, licensed contractor or registered architect or engineer. Tempe says applications must come from a licensed sign contractor.
How long is a Phoenix sign permit good for?
It becomes void if work doesn't start within 180 days or if work stops for 60 days.